2017 companies submitted the bid for the Tunnel Construction Work between Toprakkale Garden Stations, with a limit value of 326794 TL and an approximate cost of 820.624.513,99 TL, with the limit value of 1.036.066.264,85/8 KIK numbered by the General Directorate of Turkish State Railways Administration (TCDD), 835.507.349,07. DALGIÇ RAY İNŞAAT A.Ş. with an offer of ,XNUMX TL. + ATZ ENERGY CONSTRUCTION IND. VE TİC. Inc. + NEORAY CONSTRUCTION INDUSTRY AND TRADE INC. joint venture kazanIs Her.

Tender Toprakkale-Garden includes approximately 9700 mt length 5 tunnels and 2659 mt length 11 open tunnel tunneling and escape tunnels. The duration of the work is 900 (nine hundred) calendar days from the place delivery.