Ankara-Sivas between 2 hours and 30 minutes will reduce the Silk Road route 405 Km between Ankara-Sivas YHT project continues to work at full speed.

In Ankara Sivas YHT project, 300 people continue to work 7/24 day and night without cold. The rail laying and rail welding works of the Ankara-Sivas High Speed ​​Train Project, which is included in the 100-day action plan, have also accelerated. The 405-kilometer line includes 66 tunnels with a length of 49 kilometers, 27,5 viaducts of 53 kilometers, 611 bridges and culverts, and 217 under and overpasses.

In the Ankara Sivas High Speed ​​Train Project, which has a total art structure of 930 units, approximately 110 million cubic meters of excavation was carried out and 30 million cubic meters of fillings were produced.

The Ankara-Sivas line, which citizens are eagerly waiting for, will reduce the travel time between the two cities from 12 hours to 2 hours 30 minutes. The superstructure electrification and signaling telecommunication systems of the Ankara Sivas High Speed ​​Train Project continue rapidly. Physical progress was achieved in 97 percent in the infrastructure works of the Ankara-Sivas YHT Project. It is aimed that Ankara Sivas Line will be completed and put into operation in 2020 until Ramadan Feast.

The total investment cost of Ankara Sivas High Speed ​​Train Project is 9 billion 749 million TL.