Cost of Ankara Sivas YHT Project Increased 12 Times

Cost of Ankara Sivas YHT Project Increased Many Times
Cost of Ankara Sivas YHT Project Increased 12 Times

Similar to the planlessness that harmed the public in the Ankara-İzmir YHT Project, the Ankara-Sivas railway line was experienced. YHT project doubled its cost by 12: The bill of unplanned 25 billion TL

The Ankara-Sivas High Speed ​​​​Train Line project, which President Recep Tayyip Erdoğan said before the local elections on March 31, 2019, "to be opened on Ramadan Feast", has 12 times its estimated cost. The project, which was included in the investment program by the government in 2007 and laid the foundations in 2008, has still not been completed despite the intervening 13 years.

According to the news of Mustafa Bildircin from BirGün, According to the Presidential 2009 Investment Program, 2009 billion 2 million 91 thousand TL appropriation was allocated for the project in 583. In the program, the completion year of the high standard railway project, which is 455 kilometers long, was specified as 2011.

First update in 2011

However, the project could not be completed in 2011 as calculated. The project completion date was updated within the scope of the Presidential 2011 Investment Program. The completion date of the project was withdrawn to 2013 and the project amount was increased to 2 billion 212 million 895 thousand TL. The project could not be completed in 2013 and was delayed once again. While the cost of the project was increased to 2013 billion 2 million TL in 486, the year of completion was updated as 2015. The total railway line length in the project was reduced from 455 kilometers to 393 kilometers. In 2015, the Ankara-Sivas Railway Project, which returned to the snake story, was changed once again. While the cost of the project was increased to 2 billion 793 million TL, the year of completion was withdrawn to 2018 this time.

In 2018, there was a jump in the cost of the project. According to the Presidency Investment Program for 2018, the cost of the project was increased to 9 billion 749 million TL. The project is reported to be completed in 2019. It was not implemented in 2019. With the update made in 2019, the cost of the project, which was used as an election promise by the government, was calculated as 13 billion 172 million TL. The completion year of the project has been determined as 2020 this time.

The cost of the project, marked by foresight, continued to increase in 2020, 2021 and 2022. The cost increase in the project, the completion date of which was postponed until 2024, in the period of 2020-2022 is listed as follows:

  • 2020: 16 billion 456 million 54 thousand TL
  • 2021: 18 billion 105 million 310 thousand TL
  • 2022: 24 billion 946 million 378 thousand TL