Kartepe Cable Car Project Signed a Contract

Signed a Contract in Kartepe Cable Car Project
Kartepe Cable Car Project Signed a Contract

Good news came in the Kartepe Cable Car Project, which Kocaeli residents were eagerly waiting for. After the evaluation of the tender commission, the tender was concluded and the contract was signed with the company. The metropolitan will deliver the site to the company within 10 days and the works will begin.

480 WILL BE COMPLETED IN DAY

The partnership between Grand Yapı and Doppelmayr Seilbahnen, which signed the contract, needs to complete the project in 480 days. However, during the contract, the Metropolitan authorities asked the partnership to complete the project in a shorter time.

4 THOUSAND 695 METERS LENGTH

The cable car line that will run between Derbent and Kuzuyayla will be 4 thousand 695 meters long. In the cable car project, which will include 2 stations, 10 cabins for 73 people will serve.

CARRY 1500 PEOPLE PER HOUR

The elevation distance on the cable car line with a capacity of 1500 people per hour will be 1090 meters. Accordingly, the starting level will be 331 meters and the arrival level will be 1421 meters. The distance between the two stations will be exceeded in 14 minutes.