Armin Elektrik has undertaken the 29.11.2021-month maintenance activity within the scope of the work signed with TCDD Plant 7th Regional Directorate-Afyonkarahisar on 24.
Project; It consists of catenary facilities, transformer centers, traction posts and telecomand-remote control systems. On the line consisting of a total of 429 km; There are 6 transformer substations, namely Kızılinler Substation, Alayunt Substation, Tavşanlı Substation, Uluçam Substation, Selimağa Substation and Mahmudiye Substation. There are 5 chiefs. Eskişehir, Kütahya, Tavşanlı, Balıkesir and Afyon Telekomand. There are 7 Neutral Zone Posts + 24 Station Posts = 31 Traction Posts.