Everything About Ankara Sivas YHT Project

Ankara Sivas High Speed ​​Train Line
Ankara Sivas High Speed ​​Train Line

Everything About Ankara Sivas YHT Project: Total Length 393 km Ankara (Kayaş) Kırıkkale Yozgat Sivas High Speed ​​Train line has been planned as 2007-2019 years.

Yerköy Sivas Department

250 The infrastructure tender for the section with a length of Km has been made on 05.05.2008 date and 13 has been started on March 2009. In Yerköy-Sivas project, infrastructure works of 143km section were completed and final acceptance was made on 09.02.2015 date. (Construction 3: Final acceptance procedures have been completed; Physical 1:% 2; Supply 99:% 3) rates have been made in the 100 section of the project. made ready.

Ankara (Kayaş) Yerköy Department 

The tender of Kayaş-Elmadağ section was made on 24 April 2014. 15 The contract was signed on June 2016 and the place was delivered (Physical realization: 56,82%)

Elmadağ-Kırıkkale infrastructure construction works are carried out according to the contract signed on 05.04.2016 (Physical realization: 57,50%)

V7-V9-V10-V15 (4) viaduct construction works were tendered on 05.03.2013 and the contract was signed on 20.02.2014. (Physical realization: 93,14%)

Construction in Kırıkkale-Yerköy section started on 22.01.2013. It has been understood that the project cannot be completed with the contract price, liquidation consent has been obtained and the supply contract has been signed on 31 March 2017. (Physical realization:% 100) Temporary Acceptance was made on 30.10.2018.
Ankara-Kırıkkale-Yozgat-Sivas High Speed ​​Train Project is planned to be completed and put into operation in 2019 Year.

Ankara Kırıkkale Yozgat Sivas High Speed ​​Train Project Yerköy Sivas Infrastructure Construction

  • Yerköy - Yozgat - Sorgun - Yavu - Yıldızeli - Sivas
  • Yerköy - Sivas Department:
  • Project Cost: 839.713.450 TL
  • Total paid: 839.511.357,42 TL
  • Monetary Realization: 100% (Yerköy - Sivas Infrastructure Works)
  • Approximate Physical Realization:% 100 (Yerköy - Sivas Infrastructure Works)
  • Final acceptance was made on 09.02.2015.
  • Status of the Works in Yerköy - Sivas Department:
  • Infrastructure works of Yerköy-Sivas Department have been completed and provisional acceptance procedures are continuing. Yerköy-Sivas Supply construction continues in 3 section.

YERKÖY SİVAS SUPPLY CONSTRUCTION

Project Contract Price 

  • Cutting-1: 474.776.529,55 TL
  • Cutting-2: 263.021.967,40 TL
  • Cutting-3: 277.223.185 TL
  • In CUTTING 1; 21.02.2013 has been delivered on this date; Temporary acceptance on 12.05.2017, final acceptance on 14.05.2018.
  • In CUTTING 2; 23.07.2014 has been delivered on this date; Tunnel, viaduct manufacturing, artwork and earth works are continuing. Physical Realization at 99,02%.
  • In CUTTING 3; 14.03.2013 has been delivered on this date; tunnel construction, art structures and route excavation filling works are continuing. Physical Realization at 100%. Temporary acceptance on 09.02.2018, final acceptance on 11.01.2019.

Latest Situation in Ankara (Kayaş) Yerköy Department

A-) Kayas to Elmadag:

Kayaş-Elmadağ (Km 12 + 263 - 45 + 440): 4 was auctioned on September 2015. 15 On June 2016, the contract with the value of 749.924.150,00 TL was signed and the place was delivered.

Works have been started in total 12 tunnels (9.268 m.) Within the scope of the project and nearly 6.613 m tunnel excavation + support works have been completed so far. In addition, the number of 6 viaducts 5 work continues. The 39 of the total 37 culverts, the entire 8 underpasses and the 11 of the 8 overpasses have been completed and the work is underway in the others. Earthworks and infrastructure displacements are continuing.

Overall physical progress is at 58,18%.

B-) Elmadağ Viaducts:

Tender for V7-V9-V10-V15 (4) viaduct construction works was made on 289.833.710,00 with the price of TL: 05.03.2013 and 20 was signed with Doğuş Construction on February 2014.

V7 Viaduct:

Excavation-Filling works total 35 unit foundation excavation, Pile works; all 508 piles have been completed. 35 foundation concrete has been poured in foundation and side step works. Total column production in 884 m column and 1.800 meter slab production have been completed in column works.

V9 Viaduct:

Excavation and Filling Works Total 26 foundation excavations have been completed. Piles 124 piles were completed. 26 foundation concrete has been poured in foundation and side step works, total 562 m column production and 864,5 meter floor production have been completed in column works.

V10 Viaduct:

Excavation - Filling works A total of 22 foundation excavations have been completed. Pile works; Production of 168 piles has been completed. 22 foundation concrete was poured in foundation and side step works. In column works, total 1137,14 m column production has been completed, 1541 meter of 536 meter floor production has been completed and flooring production is continuing.

V15 Viaduct:

Excavation and Filling Works Total 23 foundation excavations have been completed. Pile works; Production of 315 piles has been completed. 23 foundation concrete was poured in foundation and side step works. In column works, total 839 m column production and 1.437 meter floor production have been completed.

General Physical progress is at 93,46%.

C-) Elmadag - Kirikkale: Reviews

Elmadağ-Kırıkkale (Km 45 + 440-74 + 100): 7 was auctioned on September 2015. 5 On April 2016, a contract with a value of TL 574.405.800,00 was signed.

Works have started in 5 tunnel (8.422 m.) Within the scope of the project and nearly 5.164 m tunnel excavation + fortification works have been completed so far. In addition, the production of 2 open - close has been completed. In addition, studies are continuing on the number of 2 of 6 viaducts. Earthworks and infrastructure displacements are continuing. The total number of 2 culverts has been manufactured.

General Physical progress is at 57,96%.

D-) Kırıkkale-Yerköy Section Supply Tender:

It was understood that the project could not be completed with the contract price in the Kırıkkale -Yerköy section, liquidation permission was received and the supply tender was made.

247.750.518,20 million TL. The contract for the construction of the supply infrastructure between Kırıkkale and Yerköy with the project value was signed on 31.03.2017 and the delivery date is 14.04.2017.

In project scope; total length 3.062 m. 2 viaducts, 4 underpasses, 12 culverts and 502 m. The tunnel was completed and its temporary acceptance was completed.