TCDD 5, who made presentations about the construction of the highway overpass on the Malatya - Çetinkaya Line. Regional Manager Mustafa Çalık, 9 million 506 thousand 221 construction cost of the project will be completed in December 2019 said

TCDD 5. Regional Director Mustafa Çalık made presentations about the projects and works of the regional directorate in Malatya at the 2019 Provincial Coordination Meeting. Çalık, who made presentations about the construction of the highway overpass on the Malatya-Çetinkaya Line, stated that the project will be completed in December. In his presentation, Çalık said, “TCDD 2019, whose construction cost is 1 million 52 thousand 972 TL. The project of building walkways between Fırat, Battalgazi, Hekimhan, Malatya, Doğanşehir, Kapıdere and station roads within the boundaries of Regional Directorate has started on 5; Work has been completed on the roads of Fırat, Battalgazi, Hekimhan and Malatya, but no work has been done at Doğanşehir and Kapıdere stations. A cumulative rate of physical 15.08.2018 was achieved. The studies are foreseen to be completed by 68 / 01 / 09. ”

“ÇETİNKAYA HIGHWAY WILL BE COMPLETED IN DECEMBER”

Expressing the overpass work on the Malatya-Çetinkaya Line, Çalık said, “The Project Overpass in Malatya-Çetinkaya Line Km: 9 + 506, which has a project amount of 221 million 70 thousand TL, has been started on 600. realization. The works are foreseen to be completed by 12.03.2019 / 15 / 12. ”

X 46 GATE% 100 COMPLETED IN NARLI ”

Çalık also mentioned the passage works on the Narlı-Malatya line. Regional Directorate Narlı-Malatya line Km: 2 + 26-666 + 5 level crossings (71 units) improvement work has started on 425 date and physical% 248 rate has been realized. The work is under temporary admission ”.

SIGNALIZATION AND TELECOMMUNICATION SYSTEMS ARE INSTALLED

On the other hand, Çalık also mentioned the signaling and telecommunication works in the region, and said: “The installation and construction of the roadside signaling and telecommunication systems for the Battalgazi, Kuşsarayi, Pınarlı, Şevkat, Baskil stations, whose construction cost is 1 million 732 thousand 992 TL, started on 30.07.2018. physical realization of 8% was achieved. It is foreseen that the works will be completed by 12/12/2019. ” (M Ali Günaydın - Malatyasonsöz)