Reason of Ankara Train Accident Announced: 'Rush Opened'

ankara train accident explained the reason
ankara train accident explained the reason

The experts, who were assigned to investigate the YHT accident in Ankara on December 13, 2018, nine people died, announced their reports. The report states that the main reason is that the train is put into operation before the manufacturing of the road ends on time, the project is completed and the necessary time is given. The establishment of the wrong traffic management system and taking maneuvers from east to west are other main reasons of the accident.

The experts appointed in the investigation of the High Speed ​​Train (YHT) accident in Ankara on December 13, 2018, which killed nine people, completed their reports by examining 10 folder investigation files. The main reasons explained in the report reminded Erdogan and the AKP government to speed up and rush construction for election and service shows.

Reason of Ankara Train Accident
Reason of Ankara Train Accident

'IF THE PROJECT WAS COMPLETED AND OPENED, IT WILL NOT BE DEFECTABLE'

HürriyetAccording to the report of Mesut Hasan Benli from, the report submitted to the Prosecutor's Office stated that there were 3 "root" causes of the accident. In the report, “The construction of the road was not completed on time, the scope of the project was not finished and it was put into operation without giving the necessary time. TCDD General Manager Isa A. is flawed because he opened the Ankara Sincan high-speed train line without the requirements of the ERTMS / ETCS system. The first root cause of the accident is that the line is opened with deficiencies, in other words, it is rushed to open the line. If the line had been completed and opened as specified in the project, there would be no flaws mentioned in this report and no one would be found defective. ”

'WRONG TRAFFIC MANAGEMENT SYSTEM ESTABLISHED'

The report also drew attention to the traffic management system, said that the establishment of a wrong traffic management system is the second root cause of the accident opinion.

'MANUFACTURING FROM THE EAST TO WEST'

In the report, 4 days after the shift of YHT maneuvers from east to west was recalled, kaza Taking the maneuvers from east to west is the third root cause of the accident ”. Rapor Defects who do not take the necessary measures should be investigated. For this reason, TCDD General Manager EKAY Department Head Tuna A. is flawed ”.

Armin