Sapanca Cable Car Project Has Ended

the end of the Sapanca cable car project
the end of the Sapanca cable car project

Providing a statement about the cable car project to be built in Sakarya's Sapanca District, Sapanca Mayor Assoc. Dr. Aydın Yılmazer said, “We have signed the construction license of our project, and be beneficial to our Sapanca, Sakarya and all our people.”

Sapanca Municipality and Bursa Teleferik A.Ş. and Teleferik Holding A.Ş. After the ropeway contract was signed between the business partnership, signatures were signed for the building license.

According to the contract, the company delivered the projects related to the lower and upper stations and the cable car line to the municipality. After the project reviews made by the Directorate of Housing and Urban Planning, the building license of the project was signed by the municipal authorities.

The project mainly Sapanca Sakarya and President Yılmazer wished to be beneficial to Turkey, gave information about the details of the project.

Stating that there are 2 parts of the project, Yılmazer said, “We have signed the building license of our Sapanca Cable Car Project today. The sub-station building in Kırkpınar Hasanpaşa Mahallesi will consist of ground floor +1 floor. This building has a floor area of ​​approximately 600 square meters and will include boarding-landing platform, administrative offices, management offices and masjid, toilet, kiosks and technical areas. There will be transportation by escalator and elevator between the floors and there will also be 2 fire escape. In the sub-station area, the residence area of ​​the building is designed as a completely green area. Besides, there will be a parking lot under the green area.

The upper station building will be at Mahmudiye İncebel location. The building, which will have a floor area of ​​approximately 810 square meters, will include boarding landing platform, cable car cabin garage, technical, warehouse and buffet areas. The station building here will consist of basement and ground floor. ”

Yılmazer stated that all the details are considered in order to prevent damage to the environment and nature while preparing the project, he said:

“1500 carriers will be erected on the 6 meter line, except for the station exit poles. The height of the poles is designed to be the highest mast, 47 meters, so that the trees do not cut down in the area where the line passes. The facility will install its own transformer and receive energy from the medium voltage line. In no way will it have a negative impact on city grid electricity. There will be a generator at the upper station that will meet the needs of the whole facility in order to avoid problems in power cuts. The cable car wagons will be completely transparent and will be illuminated with LED light thanks to the solar energy panels inside. We think that it will add a beautiful silhouette to the city with its transparency during the day and illumination at night. Parking lots were planned to avoid any problems in terms of traffic. Roadsides and other areas will be controlled by our municipality. ”

Be the first to comment

Leave a response

Your email address will not be published.


*