Negligence to Cause Life-threatening in Ankara-Sivas YHT Line

ankara sivas yht
ankara sivas yht

The necessary measures were not taken in relation to the deficiencies identified in 2013 for the infrastructure construction of Kırıkkale-Yerköy section of Ankara-Sivas high-speed train line.

The TCA found that the Ankara-Sivas high-speed train line, which was started at 2009, did not take the necessary measures for deficiencies identified in 2013 for the construction of infrastructure.

According to the news of Mustafa Mert Notcin from Birgün newspaper, while the investigations initiated regarding the malfunctions in the line, which is expected to be put into service in 9 and costing about 2019 billion TL, are not followed, the ground survey works carried out by the contractor firm are insufficient and a heavier ground class and support system It was stated that support was needed.

MATERIAL NOT SUITABLE FOR USING THE FILLER

The auditors emphasized that most of the materials supplied for use in soil works cannot be used in fillers. Auditors who stated that the line needed to be used for earthworks should be taken from the quarry, and that this would lead to an increase in the amount of excavation related to the railway line. Auditors noted that the studies could not be carried out in accordance with the work program due to all these determinations and alternative routes were being searched for while the construction work was under way.

In the report, it was stated that all the project studies and manufacturing process should be investigated. In the report that underlined that the necessary measures should be taken to prevent the shortcomings in the audit report of the Court of Accounts of 2013, the deficiencies reported in the report are as follows: hazır, hazır Significant differences between the ground classifications in the viaduct foundations and tunnels and the existing approved project, onay, lam The emergence of significant revisions to another firm by re-evaluation of the revised project, without sufficient ground drilling studies ." (One day)