TCDD II. According to the announcement made by the Regional Directorate, TCDD Ankara (YHT and Conventional), Eskişehir (YHT and Conventional), Konya (YHT), Niğde, Kayseri, Kırıkkale, Bilecik (YHT), Sakarya (YHT) Railway lines under the supervision of specialized personnel and special train To protect the ballast cleaning and pulling the pulled and pulled rail vehicles in a negative way and self-growing to remove the grass will be applied chemical pest control.

Although all the necessary precautions should be taken in order to ensure that the suspension to be used in chemical pesticides is not harmful for human and animal health, following the spraying, the railway line should not be grazed for one week near the 10 meter and the grass should not be harvested.

PHARMACEUTICAL PROGRAM
01.10.2018 Marşandiz Gar field

02.10.2018 Marşandiz-Eskişehir (Hasanbey) spraying

03.10.2018 Hasanbey-Marşandiz return and Marşandiz-water filling

04.10.2018 Irmak-Yerköy spraying

05.10.2018 Yerköy-Kayseri spraying

06.10.2018 Kayseri Gar field-variant-Sivas side spraying

07.10.2018 Kayseri-Niğde-Ulukışla spraying

07.10.2018 Clock 20.00 Ulukışla -Kayseri-Ankara directory empty return

08.10.2018 Ulukışla -Kayseri-Ankara directory empty return

09.10.2018 Ulukışla -Kayseri-Ankara directory empty return

10.10.2018 Marşandiz purchasing and stock kont. Dir. way water filling

10.10.2018 Clock 21.00 -Marse-Esk Line YHT Line spraying

11.10.2018 Clock 06.00 -Maşandiz-Eskişehir YHT line spraying

11.10.2018 Clock 21.00 Eskisehir-Alifuatpasa YHT sprayer

12.10.2018 Clock 06.00 Eskisehir-Alifuatpasa YHT sprayer

12.10.2018 Watch 21.00 Alifuatpaşa-Eskişehir YHT line spraying return

13.10.2018 Clock 06.00 Alifuatpaşa-Eskişehir YHT Line return from spraying

13.10.2018 Daytime water filling

13.10.2018 Clock 21.00 Eskişehir-Alifuatpaşa YHT Line disinfection (Other line)

14.10.2018 Clock 06.00 Eskisehir-Alifuatpasa YHT sprayer (Other line)

14.10.2018 Watch 21.00 Alifuatpaşa-Eskişehir YHT line spraying return

15.10.2018 Watch 06.00 Alifuatpaşa-Eskişehir YHT line spraying return

15.10.2018 Hour 21.00 Eskişehir-Marşandiz YHT line spraying (Other line)

16.10.2018 Hour 06.00 Eskişehir-Marşandiz YHT line spraying (Other line)

16.10.2018 Clock 21.00 Marşandiz -Konya YHT line sprayer

17.10.2018 Clock 06.00 Marşandiz -Konya YHT line sprayer

17.10.2018 Hour 21.00 Konya-Marşandiz YHT return from spraying line

18.10.2018 Hour 06.00 Konya-Marşandiz YHT return from spraying line

18.10.2018 Clock 21.00 Marşandiz -Konya YHT line sprayer (Other line)

19.10.2018 Clock 06.00 Marshal-Konya YHT Line spraying (Other line)

19.10.2018 Hour 21.00 Konya-Marşandiz YHT return from spraying line

20.10.2018 Hour 06.00 Konya-Marşandiz YHT return from spraying line