The Foundation of Karamürsel City Square Bridge Interchange Has Been Launched

Kocaeli Metropolitan Municipality realizes the projects that will relax the city traffic. Especially intersections on intercity highways make traffic flowing and also prevents traffic stress in cities. One of the intersections at the key points of the city comes to Karamürsel. The D-130 highway, which is one of the important routes of intercity passenger and logistic transportation, is arranged in the form of a sunken-exit in the Karamürsel city square. The groundbreaking ceremony was held for the Karamürsel City Square Köprülü Junction where the center of the city will gain integrity. Kocaeli Metropolitan Municipality Mayor Ibrahim Karaosmanoglu said they would open a bridge junction.

INTENSIVE INTEREST IN THE FOUNDATION OF THE FOUNDATION
Deputy Prime Minister Fikri Işık, Kocaeli Metropolitan Municipality Mayor Ibrahim Karaosmanoğlu, Metropolitan Municipality Deputy Mayor Zekeriya Özak, Metropolitan Municipality Secretary General İlhan Bayram, Deputy Secretary General Doğan Erol, Ak Parti Kocaeli Provincial Vice President Abdullah Eryarsoy, Karamürsel District Governor Ahmet Narinoğlu, Karamürsel Mayor Ismail Yildirim, participated in the protocol and citizens.

LIGHT: TRANSIT TRAFFIC WILL REDUCE THE LOAN
Deputy Prime Minister Fikri Işık, who attended the groundbreaking ceremony by coming from the martyr funeral in Kastamonu, stated that no matter where the terror was, the head would be crushed. Işık im I was a brother who studied in middle school in Karamürsel for a year. I walked by that road for a year. When the AK Party came to power, we did not have a divided way here. Remember, they started a road from Izmit to Golci. A lot of corruption claims were left unfinished. The room was a road to earthquake. As soon as we came to power, we turned this road into a double road to Yalova. Now the room does not correspond to your need. Thanks to Ibrahim Bey, the Mayor of the Metropolitan Municipality, this project is being carried out for this center of Karamursel with our consultations. This center of our Karamürsel is very cramped. Traffic lights Karamursel brings a very serious load. The decision of this project was taken in order to reduce the burden of transit traffic by sinking.

PRESIDENT: WE WILL OPEN THIS TUNNEL FOR YEARS
Speaking at the Groundbreaking Ceremony, Mayor Karaosmanoğlu said, ören We believe that we have made good services in the infrastructure of our cities from our villages to the upper structure, environment, social and educational services. We receive the appreciation, gratitude and prayer of our people. We also fulfill our promises and promises. We have never left any work that we have started. I hope this will end before the end of the year. We're gonna open this tunnel for Christmas. Thus, this tunnel will bring together the upper section of the lower part of our Karamürsel. The demands and demands of our people are very important for us. We produce projects according to the demands and demands of our people. Biz

COMPLETED IN THE YEAR END
The project, which will unite the two sides of the D-290 with the 130 meter closed part, will add integrity to the district. Within the scope of this tender, the municipality was awarded the lowest bid with 41 million 967 thousand TL. Completing the construction site before the start of pre-production traffic transmission work to complete the project by the end of the contractor firm.

290 METER CLOSED SECTION
The dalçin project, which has started to be built in the Karamürsel City Square region, will be implemented on the D-130 highway. The bridge junction with tunnel transition, which will be 19 meters wide, will have a 290 meters long closed part. The project will be implemented as a 2 × 2 lane branch. In addition, with the project, 130 meters of the D-710 highway will be reorganized.

21 THIN 700 TON ASPHALT
Under the project, 17 thousand 470 cubic meters of various concrete, 5 thousand 650 tons of iron is planned to be used, while the floor will be pile 18 thousand 250 meters. In the project 28 thousand 500 tone base layers, 21 bin 700 tone asphalt, 52 thousand 500 square stone mastic asphalt will be laid. At the intersection 4 bin 750 flooring parquet, 6 bin 500 meter border will be used. In the study 3 bin 110 meter drainage, 2 bin 450 meter sewage and 2 bin 640 meter to be made of drinking water line.