OMU Reaches Tram in June

The light rail system of the Samsun Metropolitan Municipality is completed in June. The rail system to be delivered to OMU will be 3 with 6,4. Also the municipality will take the 10 new tram for this stage.

Samsun Metropolitan City Council 2018 Year April 7. Combination of 1. The session was held yesterday at the Metropolitan Municipality Assembly Meeting Hall.

At the parliamentary meeting chaired by Turan Çakır, the Deputy Chairman of the Assembly, the agenda item of the 50 was discussed. During the meeting, the 2017 Annual Activity Report of the Municipality of Samsun and the 2017 Year Audit Report as well as the other 48 article were discussed. At the meeting, Ahmet Arslan, Head of Financial Services, presented the activity report of the municipality. Ahmet Arslan talked about many works of the municipality from infrastructure to superstructure, social activities and cultural activities.

COMPLETED UP TO JUNE

Speaking of the Municipality's Transportation and Infrastructure Projects, Ahmet Arslan gave information about the latest status of the Kurupelit Last Stop - University Life Center Light Rail System Project. Ahmet Arslan said, “After the completion of the Tekkeköy line in the light rail project, the necessary studies have been initiated for the tram to go to the university; In this context, the tender for the 3rd phase (between Kurupelit Last stop - University Life Center) Light Rail System project was held on May 2, 2017. Currently, the front of the hospital tube passage works, cable channel productions, the construction of the rail platform catenary foundations continue and the project, which is 6,4 kilometers long, is planned to be completed by June 2018. ”

40 TRAIN SERVICE WILL BE GIVEN

Ahmet Arslan also said about the project; “In this project, 6,4 kilometers of double track railway, 10 stops (Lodgings, Polyclinics, Vocational School, Faculty of Dentistry, Faculty of Theology, Faculty of Agriculture, TEKNOPARK, Faculty of Engineering, Faculty of Arts and Sciences and Student Dormitories), 6,5 percent slope There are 150 viaducts with a length of 380 meters - 2 meters. In addition to the existing trains, 11 trains are planned to be purchased, and the Light Rail System will serve with a total of 40 trains with the arrival of new trains ”. In addition to the Activity and Audit Reports, other agenda items were also discussed and resolved.