Flatten for high-speed train

The railway, which is planned to pass over the bridge, will pass through forest, agriculture, pasture and rural settlements.

Controversial project 3. The Environmental Impact Assessment (EIA) process of the Gebze-Sabiha Gökçen-YSS Bridge Railway Line Railway Project, which is planned to pass over the bridge, has started. According to the file submitted to the Ministry of Environment and Urbanization, the project will be 56 km long. Within the scope of the project, the expropriation will be carried out on an average area of ​​25 meters, approximately 50 meter meters from the right and left of the line along the route. The railway project passes through forest, agriculture, pasture, rural settlement areas.

According to the project submitted to the Ministry, the line will pass through the boundaries of Tuzla, Pendik, Sultanbeyli, Sancaktepe, Maltepe, Atasehir, Umraniye, Cekmekoy and Beykoz District respectively and 3. The connection to the railway line on the bridge will be completed.

In the project file, the Gebze-Sabiha Gökçen-YSS Bridge YHT Line Railway Project is connected to the existing high-speed train line within the boundaries of Tuzla district and is located on the 3 route between Ankara and Istanbul. Although it provides direct access to the airport, Pendik and Sabiha Gokcen Gar stations, which are planned to be built within the borders of Istanbul Province, will relax the urban transportation 'expressions were used.

16 tunnel, 5 viaduct will

Within the scope of the project, 38 tunnels with a total length of 955 thousand 16 meters and 631 viaducts with a length of 5 meters will be built. Underpasses and overpasses will be constructed on the railway line at the intersections with the highway. Two station points will be established in Pendik and Sabiha Gökçen in the project. The project will include 2 different lines, round trip. The distance between these lines will be 4.5 meters and the platform width will be 14.5 meters. The cost of the project was determined as 4 billion 853 million 700 thousand TL. The EIA process has begun for a project that takes the life of the natural life with the 3rd bridge project that plots the Northern Forests.

Source : www.cumhuriyet.com.t is