The new stage starts in Konak Tramway:Karşıyaka Izmir Metropolitan Municipality, which has completed the manufacturing operations in the Tramway and started its preliminary operations, works at Konak Tramway at an intense tempo. Having completed the first 2 stages on the Poet Eşref Boulevard, the 3rd and 4th stage productions covering Lausanne Square will also start the 5th and 6th stages starting on Saturday.

The works of the Izmir Metropolitan Municipality tram project that will bring new breath to the urban transportation are in full swing. 8.8 kilometers Karşıyaka Metropolitan Municipality, which offered the tram to the public last month, is working hard to finish the Konak Tram line. Rail laying works were completed in two stages at the 460-meter section of Poet Eşref Boulevard between Lausanne Square and Alsancak Hocazade Mosque. Within the framework of the 3rd and 4th stage works, double-sided rail laying works will be completed on Friday, May 100th at the 5-meter section of the Lausanne Square.

Manufacture starts in the direction of Montreux
Within the framework of the 6th and 5th stage works that will start on Saturday, May 6, two-way rail laying will be carried out in the 130-meter section between Montreux Square and Lausanne Square. During the productions, which are planned to take 30 days, vehicle traffic will be provided from the opposite lane in two directions. Later, the productions in the direction of Montreux Square from Lausanne Square will be completed.

200 meters close to traffic
On the other hand, the line manufacturing works that will reach the Alsancak Hocazade Mosque will continue on Ali Çetinkaya Bulvarı. 6, 2017 and 1 streets with Dr. The area will be accessible via Mustafa Enver Bey Street, Şair Eşref and Ziya Gökalp Boulevard.

Be the first to comment

Leave a response

Your email address will not be published.


*