Akçaray's work does not slow down

Akçaray works does not slow down: Kocaeli Metropolitan Municipality conducts Akçaray tramway works simultaneously in many parts of the city.
Kocaeli Metropolitan Municipality, Akçaray carries out the tram works simultaneously in many parts of the city. Tramway works are carried out in coordination with different teams according to their quality. Within the scope of the ongoing tram works, 15 team is involved in the production of rail assembly, iron works, welding, pavement manufacturing, transformer buildings manufacturing, electricity, water and natural gas.
Tramway works of the Metropolitan Municipality which will strengthen the city's transportation network continue at full speed. Within this scope, 750 meter rail installation was carried out on the 650 meter section of Elzem and Hanlı Street, where the works started first. Electricity, natural gas, telecom, rain water, drinking water and wastewater lines were completed. The section intersecting with Seymen Street was paved and opened to traffic. Pavement and road works completed. 9 pieces of kataner mast foundation was completed in the middle of the line in Hanlı Street.
Pavement and road works completed
Xmasun meters rail was installed on the 550 meter section of Salkım Söğüt and Sarı Mimoza Street. Electricity, natural gas, telecom, rain water, drinking water and wastewater lines were completed. The pavement and road works are completed. While the carriage works of the transformer in the region are finished, the wall plaster works continue.
On the Necip Fazıl Street, the 650 meter of the 525 meter rail line was installed. Electricity, natural gas, telecom, rain water, drinking water and wastewater lines were completed. The return to Yahya Kaptan was paved and opened to traffic. The pavement and road works were finished. 6 pcs kataner mast base manufacturing is completed in the middle of the line
Rail assemblies in progress
The 650 meter rail was assembled at the 500 meter section of the GMK Boulevard Adnan Menderes Boulevard. Electricity, rain water, drinking water and wastewater lines were completed. Natural gas, Telecom lines to the end of the 600 meters of the 100 meters of the pavement was completed. In the middle of the line, the 17 cataner direct foundation manufacturing was made ready. The 700 meter rail was assembled on the 25 meter section of the section between the Adnan Menderes Boulevard and the East Barracks. Production of electricity, storm water, drinking water and wastewater lines was completed while the 300-meter road production was completed. Natural gas, Telecom lines have come to an end. 225 meter rail installation was carried out on the 600 meter in the East Kışla-Şehit Rafet Karacan Street. Infrastructure works, pavement and road works in Köse Street and 1000 pcs kataner direct foundation in the middle of the line were completed. D-750 10 meter rail assembly was performed on the 100 meter on the side of the highway side, 600 meter part was bushed. Electricity, natural gas, telecom, rain water, drinking water and wastewater lines were made ready for production. Thursday Market-Hafız Binbasi Street Thursday Street junction was paved and opened to traffic. 350 meter rail installation, 100 meter rail assembly was done in 550 meter section, 100 meter rail was cut. While the production of rain water, drinking water and wastewater lines was completed, the carrier carcass works of the transformer were completed.
Expropriated buildings were destroyed
The demolition of the buildings expropriated on Şahabettin Bilgisu Street was completed. Preparations are being made to enter the line excavation when the rain water, drinking water and wastewater lines are finished. 1000 meter rail was installed in the 150 meter section between the Central Bank and Sekapark. 100-meter section of the line excavation work, transformer carrier carcass works are over. At the warehouse site, the main building of the workshop building continues. 100 / 2 of the base works, 3 / 1 of the basement column works have been completed. While the foundation of the water tank building was laid, the orders of the prefabricated carrier elements were given and the production was started. Worker carcass works of the transformer are finished, and the wall plaster works continue.