Bursa Fast train line hit the google map 447 million damage

Bursa Fast train line hit the google map 447 million damages: 75 km of the 50 kilometer high-speed train line between Bursa and Yenisehir has changed. Due to this change in the state, the 447 million pounds were damaged.
CHP deputy Haydar Akar, "a project prepared on the Google map," he reacted.
The scandals in the High Speed ​​Train tenders are not backed up. The route of the Bursa-Yenişehir YHT line was changed many times. 75 kilometer road 50 kilometers of the lake in front of the lake, agricultural land, greenhouse, building, the mountain was rebuilt. At the beginning of the tender, the line that will cost 393 million TL reached 870 million TL. The loss of public interest went up to 75 miles and even to 477 million.
AUDIT REPORTS
TCDD accounts in the Parliamentary Commitee Commission of the million-dollar YHT auctions came to the agenda. In the 2011, the Court of Accounts reports on irregularities detected in the Bursa-Yenişehir line. It has been revealed that the scandal in 2012 has not been asked to account for the 4 years. TCDD General Manager İsa Apaydınreiterated that the scandal is still being investigated by the Ministry of Transport.
5 COMES 30 PERCENT IN YEARS
Speaking about the scandal in the Parliamentary Commission of the Parliamentary Assembly CHP Kocaeli Deputy Haydar Akar, "One night someone thought of the Bursa-Yenisehir line to come. I walked from a project prepared on a Google map to tell you sincere. 393 million TL to work until now 560 million pounds spent. On the 75 of the 30-kilometer line, physical progress has been achieved, with the 70 being behind. The 75 kilometer of the 50 kilometer line has changed. On the one hand, 'there is a lake, we can not pass here,' 'he said on the other hand,' There are farmland, we can not pass here, '' he said.
Wasn't there agricultural land before the tender?
Fahrettin Oğuz Tor, the MHP member of the KIT Commission, reacted to a change of route on the 75 kilometer of the 50 kilometer line after the contract was signed. Tor said that the costs have been doubled because the infrastructure works were not done before the tender, için I don't know how it would be, but it wouldn't work. In other words, it is not possible for reason to take logic. The fact that the project line passes through very valuable farmland, orchards and greenhouses, affects DSI's plans for the annual drinking water network of Bursa 20 in So, is it not possible to look at where these lines are going through when examining this tender document? Didn't these lands, greenhouses have been around here? S.