About 3.

3.Havalıanı Wondering About the Ataturk Airport due to lack of capacity 13 2012 XNUMX date of the Council of Ministers decided on the new airport.
Istanbul Regional 3. The name of the airport is the name of the Ministry of Transportation. Although the official name of the airport is not yet known, it has been proposed to give the name Pilot Vecihi Hürkuş to the airport.
The project is expected to be the world's highest passenger capacity by crossing the Atlanta International Airport, which serves 2018 million passengers annually, by the end of 94.
Construction process
Work on the airport is ongoing. The construction process will consist of 3 stage:
1. Phase (latest 42 will enter service after month)
2 pieces independent parallel runway (3750m60m)
1 Piece Cross Runway (3750m
60m)
3 pieces of parallel taksirut (3750m45m)
High speed and connection cabs
apron
Terminal building
Air traffic
Communication and meterology systems
other service buildings and systems
2. Stage
1 independent runway (3750m)
60m)
1 pieces of parallel taksirut (3750m45m)
3. Stage
1 units independent runway (3750m) to Tayakadın-Yeniköy side
60m)
1 pieces of parallel taksirut (3750m45m)
To the south of the existing settlement 1 pieces cross tracks (3750m
60m)
1 pieces of parallel taximeter (3750m * 45m)
3. 2 bin truck at the airport construction site, the 400 work machine is working continuously. On the one hand, while the construction works are going on, on the other hand the design details become clear.
In terms of passenger capacity, it will continue to be the largest aviation center in the world. After five months of political uncertainty, the mega project, which made various comments about the future, continues without any hype. The work for the airport, which the world's aviation sector has been waiting for with its passengers, has won the tempo. In the first phase of the project with total 4 phase, ground correction, excavation and superstructure construction works are ongoing. During the project, dozens of construction sites on the 1.800 excavation truck is seen in intensive work, the construction site daily 1 million 200 thousand cubic meters of soil movement is performed. Three independent parallel tracks, taxiways, apron, terminal building, air traffic, communication and meteorology systems and other service buildings will be implemented in the first stage of the airport. 898 white collar and 8 bin 468 blue collar 9 bin 366 staff work in the project.
10 billion euro investment
The first phase of the project, which is foreseen to be 10 billion 247 million euros of investment value, is expected to be operational in the first quarter of 2018. IGA, 6 has provided 4.5 billion euro loans from the bank.
3.500 aircraft will land
The airport is planned to have 3.500 landing and take-off capacity. The project will be the world's aviation center.
The largest terminal
The main passenger terminal building, 1,3 will be the largest terminal building under a single roof of the world with a square meter of square meters. This terminal is intended to serve 90 million passengers in the first place. The annual passenger capacity will reach 2028 million in 150. Large-bodied airplanes that are not able to land at existing airports will also be able to land at the New Airport.
Who won the airport tender?
The tender, Cengiz-Limak-Kolin-Mapa-Kalyon Joint Venture Group, won 25 billion 22 million Euros for the annual rent of 152.
Istanbul New Airport how much will it cost?
Istanbul 3. The approximate investment cost of the airport was announced as 9 billion 500 million dollars. A total of 10 billion 247 million Euro investment will be made for Istanbul New Airport and the passenger service will be opened in stages.
3. Where's the airport?
The third airport is located on an 80 million square meter area between Yeniköy and Akpınar villages on the European side of the Black Sea in Istanbul. The new airport will be the world's largest airport.
3. How to get to the airport?
The high-speed train will end at the transfer station at the airport. In addition, at the transfer station will be the Airport Metro, the third passage from the Bosphorus, the rail system, the AirRay, the bus lines connecting to the city center and the car park.
Taksim - 3. How many minutes will be from the airport?
The new airport will be connected to Taksim via rail system. This rail system will pass through the route of the old railway line. Transportation will be provided from all parts of Istanbul via public transport. From Taksim to the airport will be reached in 15 minutes.
When will the first phase of the New Airport end?
3. In the 42 month, the first phase of the airport will be launched in the winter 2016 (2016 end of October) IATA flight tariff period. In the first stage; 2 pcs independent parallel runway (3750m x 60m), 1 pcs cross runway (3750m x 60m), 3 pcs (3750m x 45m), high speed and connection cabins, apron, terminal building, air traffic, communication and other service buildings will be implemented. The project will be constructed in four phases.
3. When will the construction of the airport end?
Istanbul's 3. The airport is planned to be completed by the end of 2018.
How will Istanbul New Airport be?
Istanbul 76 spread over a total area of ​​3 million square meters. Within the scope of Airport Project; 6 pieces of independent runway, 4 pieces apron and 16 pieces of taxiway, total of 1,5 million square meters closed area 4 domestic and international terminal buildings, each with 85 meter height 3 units of Technical Block and Air Traffic Control Tower and 8 pieces of Apron Surveillance Tower, DHMI service building and all other facilities required for the airport (fire brigade, construction machinery and auto garage, safety building, regulator building, power center, heat center, water tank, customs building) will be made.
3. What is the capacity of the airport?
Within the scope of the project, 52 million 210 million square meter application construction area will be excavated and filling works of 939 million cubic meters. Istanbul 3. Once the Airport Project is completed, the 165 passenger boarding bridge will have an annual 500 Million passenger capacity with an 150 aircraft capacity.
At the airport, the 1,5 passenger terminal boarding terminal, 165 control tower, 3 terminal building, 4 independent runway, 6 taxiway and 16 airplane will be equipped with 500 million square meter terminal area.
3. How was the airport designed?
5 will be installed on a total of 7 km 3 hectares in km x 500 km. 1.100 hectares in connection with the airport will have a high-tech industry and trade area. Flight paths will be positioned to minimize noise. The terminal building was designed as a green building.
3. How will the airport be illuminated?
The use of glass envelopes will provide maximum daylight input in the middle of the terminal building, reducing the need for artificial lighting. The terminal building will be the 'smart building' that uses maximum power to minimize electricity use.
3. How will the airport be heated?
Electricity and heating needs will be met by the central heating and power generation unit using most of the garbage produced by the airport.
3. What are the most important facilities of the airport?
The airport will have an important facility in 5; terminal building, runways, transfer station, repair facilities and hangars and air transport facilities.
3. How many mezzanine floors will be found at the airport?
350 mx 1.500 is a building with a mezzanine, 6 is a multi-storey building, low level of arrival and a second level of levitation will be the total 4 terminal, authorities and management will be found for the use of aces.
Will there be a shopping center at the third airport?
3 star hotels, commercial office buildings, trade fair grounds will be located on a large shopping facility, upper 5 floor. 'Special economic zone' will be established for international finance and commercial transactions.
Third Airport meets international aviation standards?
It will be designed in a streamlined way to minimize wind speed. The outer tissue will be covered with galvanic tissue, which will serve as the solar collector.
There will be 3,5 runway with 4 runway parallel to the Black Sea, 4 runway parallel to the Black Sea and 2 runway perpendicular to the Black Sea.
Flight routes will be positioned in a way to prevent flying over the proposed city.