TCDD 3. The railway renovation works carried out at the Regional Directorate

TCDD 3. The railway renovation works carried out at the Regional Directorate were examined: Road renovation works were carried out between Alasehir and Esme stations by a rapid road renewal machine.

  1. Regional Director V. Murat Bakir, Road Department Vice President Ali Ozturk and 3. Region Road Service Manager V. Osman Aksun 3. The Regional Directorate of 2015 explored the road renovation works with the fast road renewal machine between the Alaşehir - Eşme stations, which are among the planned investments of the year.

They went to the place of Uşak-Eşme and completed the inspections. Up to now 17600 meter road renewal has been made and the restoration work continues.

 