$ 200 million loss occurred in Üçyol - Üçkuyular metro line

200 million dollars of damage occurred in the Üçyol - Üçkuyular metro line: Stating that the mistakes made during the project, tender and construction phase of the Izmir Metro brought an additional cost of 200 million dollars, Hanefi Caner said, "This damage was paid out of the pocket of Izmir."

The Izmir Metro, which was completed by the Izmir Metropolitan Municipality in 7 years only and was put into service without fire detection, extinguishing and leakage current collection system, filed as a bomb on the agenda by the Ministry of Internal Affairs to send property chief inspector to İzmir. Retired bureaucrat Hanefi Caner, who served as the head of the transportation and traffic department for 20 years during the periods of Yüksel Çakmur and Burhan Özfatura, one of the former mayors of the Izmir Metropolitan Municipality, contributed greatly to the timely commissioning of the metro line Üçyol-Bornova Metro Line, made striking statements regarding the agenda. . Caner; He claimed that Üçyol - Üçkuyular Metro reported the faults he saw during both project and construction by photographing them, but these were not taken into consideration by either Metropolitan Mayor Aziz Kocaoğlu or other bureaucrats.

TUNEL WAS TOLD ON TWO TIMES
Reminding that the metro tunnel was torn twice in 2011 and 2012 due to the mistakes made during the project and manufacturing phase, Caner said, “The mistakes made during the project, tender and construction phase brought an additional cost of 200 million dollars to the municipality. This money came out of the pocket of Izmir, not anyone else. No matter who thinks, you have stolen the money of the state, and you gave it to the contractors for free. I think it's the same thing. This is an absolutely inexcusable mistake. Here, the biggest damage has been done to İzmir and İzmir. As an İzmirite, I would definitely not want to be in Üçyol - Üçkuyular Metro at the time of the earthquake. "I don't find this part of the subway safe," he said. Hanefi Caner, the head of the former rail system department, who was sled in the municipality in 2004 and was not even required to consult for 11 years, said that he sneaked into the subway at night during the time he was on the sled and he took a photo of the mistakes during the manufacturing phase. Caner, who claimed that the Üçyol - Üçkuyular line was absolutely unsafe, claimed that the subway tunnel was shaved to catch the gauge during the construction phase and as a result, the equipment in the tunnel was damaged. Caner; “Inonu street was closed to traffic for a long time. Many tradesmen went bankrupt. He became unable to pay his rent in many trades. Citizens living in that area had great difficulties entering their homes and apartments. In addition to the financial aspect of the business, social cost is not calculated. ”

TWO COMPONENTS
Stating that the deadliest error in the construction of the subway was made at the tender stage, the line with a total length of 5.5 kilometers was tendered in two separate parts instead of tender, he continued his words as follows; “The biggest mistake was made at the tender stage. Instead of a competent company that knows the entire business, the entire line has been tendered to companies that have not made any metro or tunnel so far. During the tender stage, renowned specialist companies conveyed the errors and reservations made in the tender specifications to Büyükşehir one by one. But these were always ignored. As a result, these firms did not even participate in the tender when their warnings were not taken into consideration. So what happened? Inexperienced companies, many of which have not even built a tunnel, have not finished the subway turnkey, have offered these works at cheap prices. As a result, they hurt themselves because they did not know the job, they asked for extra money from the Municipality. When they couldn't get it, they left the job and ran away. ”

Be the first to comment

Leave a response

Your email address will not be published.


*