Spanish delays for Marmaray

The Spanish delays to the Marmaray: Marmaray Halkalı and Gebze line extension works came to a halt. TCDD suspended the project, which is planned to be completed in 2015, after the financial problems of the Spanish contractor firm slowed down the work.

Marmaray Halkalı and Gebze extension projects were shelved.

According to the news of Mustafa Gürbüz from Aydınlık Newspaper, the Spanish Company, which won the tender, slowed down the works, even stopped, citing the increase in costs. This information was based on a senior official from TCDD.

TCDD expected to end in 2015 Halkalı and Gebze suspended extension projects. According to the project Kazlıçeşme-Halkalı and the suburban lines between Haydarpaşa-Gebze were to be improved electrically, mechanically and structurally and integrated into Marmaray.

The Spanish company also owns the railways iyleştir to tender in Turkey. The improvement projects that the company started by removing the rails are still not finished.

“Sirkeci-Halkalı"Haydarpaşa-Gebze" and "Istanbul-Edirne" train services were stopped.

Speaking to the official Gazette bright, Istanbul-Ankara High Speed ​​Train line said that it is costly Turkey. TCDD officials, the High Speed ​​Train budgets for all of Turkey's rail can be improved, he said.

Be the first to comment

Leave a response

Your email address will not be published.


*