General Directorate of Highways Investments

General Directorate of Highways Investments: Highway Works 2014 Year Targets.In order to make improvement design projects, first of all, the engineering consultancy services carried out in the history of 18.07.2011, the maintenance, repair and strengthening of the suspension bridges are planned. has been made by the company and the result of the work according to the needs of the construction and construction control tenders have been made.
Within the scope of the engineering and consultancy services to be realized, precise measurements, analyzes and tests will be carried out on the Bosphorus and FSM Bridges and technical specifications will be prepared based on the construction projects and the construction contracting services will be completed in 2013. As a result of this study, construction bidding will be made according to the improvement needs that will occur in Bosphorus and FSM Bridges.
The contract for the construction of a major repair and structural reinforcement project of the Bosphorus and Fatih Sultan Mehmet Bridges was signed on 25 November 2013. The contracting and consultancy work of the construction work was tendered and the contract was signed on 25.02.2014. Within the scope of this work;
Bosphorus Bridge:
- 236 hanger ropes (Diagonal hanger ropes will be made vertical)
- Strengthening the towers (the towers will be strengthened with internal steel plates.)
-The repair and strengthening of some parts of the ably
- Superstructure renewal (asphalt works)
- Establishing a dehumidification system against corrosion for main cable and anchorage rooms
- Electromechanical works (elevator, wiring etc.)
At the FSM Bridge:
- Paint works (full painting of the bridge)
- Main works such as the establishment of a dehumidifier system against corrosion for the main cable and anchorage rooms will be carried out.
In 2014, in the Build - Operate - Transfer project;
- Accelerating the construction works on the Gebze - Orhangazi - İzmir (including İzmir Bay Crossing and connection roads) highway, which is assigned,
- Speeding up the construction works in the İzmir - Manisa State Highway Sabuncubeli Tunnel project,
- North Marmara Motorway (including the 3rd Bosphorus Bridge) Project room - Speeding up the construction works in the Paşaköy (including the 3rd Bosphorus Bridge Project),
- Project including Kurtköy - Akyazı (including connection roads) and Kınalı - Odayeri (including connection roads) including the Northern Marmara Bridge is planned to be tendered within the scope of the build-operate-transfer model.
- The Ankara - Niğde Motorway Project has been applied to the High Planning Council (YPK) and it is planned to be announced after the YPK decisions are issued.
- Ankara - Samsun Highway (Ankara - Delice Section),
- Kınalı - Tekirdağ-Çanakkale-Balıkesir Motorway,
- Aydın - Denizli - Burdur Motorway,
projects were applied to the Higher Planning Organization. Regarding these projects, revision studies are carried out in the feasibility reports in line with the opinions conveyed to the General Directorate by the Ministry of Development.
- Ankara - İzmir Highway,
- Afyon - Antalya - Alanya Highway,
- Sivrihisar - Bursa Highway,
- Şanlıurfa - Habur Motorway and Diyarbakır Connection,
- Gerede - Gerede - Merzifon Section of the Gürbulak Highway,
- Ankara - Samsun Highway Delice - Samsun Section
- Gerede - Merzifon - Gürbulak Section of the Gürbulak Highway
- Aydın - Denizli - Denizli - Burdur Section of Anatlaya Highway
projects' feasibility, corridor survey, EIA (Environmental Impact Assessment) and preliminary project works were tendered. The construction tenders of these projects will also be carried out with the build - operate - transfer model in 2014 and later years.
Highway Project and Consultancy Works:
Studies in 2013: The Project and Consultancy Branch Directorate conducted 2013 projects and engineering services under the main project title of 1 Study Project Consultancy Services in the 17 Investment Program. Total project costs are 386.4 million liras. As of the end of 2013, 170.4 million TL has been realized. The realization rate is 44%. In 2013, a total of 5.9 million lira was provided and all of this allowance was spent.
Ongoing project services in 2013 İzmir Ring Road (between Çiğli - Aliağa), Aliağa - Çandırlı Motorway, Ankara-Kırıkkale - Delice Motorway and Kırıkkale Ring Road, Ankara - İzmir Motorway, Kınalı - Tekirdağ - Çanakkale - Savaştepe Motorway, (Ankara - İzmir Dist.) - Bursa Motorway, (Ankara - İzmir Dist.) - Afyon - Antalya - Alanya Motorway, Şanlıurfa - Habur Motorway, Gerede - Merzifon Motorway, Delice - Samsun Motorway Aydın - Denizli - Burdur Motorway (Denizli - Burdur Section) and Merzifon - Gürbulak Highway Project Engineering Services Project studies have continued. In 2013, in the preparation of EIA Reports within the scope of Surveying and Project Consultancy Services, a tender for the Service Procurement Work was made in 2 groups and a group tender is planned for 2014.
2014 Targets: The project amount of 2014 Study Project Consultancy Services included in the Investment Program in 1 is 409,5 million liras and the allowance for 2014 is 18 million liras. In 2014;
- İzmir Ring Road (Between Çiğli and Aliağa) Km: 0 + 000-29 + 000,
- İzmir Ring Road (Between Çiğli and Aliağa) Km: 29 + 000-47 + 000,
- Aliağa - Çandarlı Motorway,
- Ankara - Kırıkkale - Delice Highway, Kırıkkale Ring Road (between Ankara - Kırıkkale),
- Ankara - Kırıkkale - Delice Highway and Kırıkkale Ring Road (between Kırıkkale-Delice and Kırıkkale Ring Road),
definite project and feasibility works
- Ankara - İzmir Motorway (between Ankara and Dumlupınar),
- Ankara - İzmir Motorway (between Dumlupınar and Manisa),
- Kınalı - Tekirdağ-Çanakkale - Savaştepe Motorway (between Kınalı-Çanakkale),
- Kınalı -Tekirdağ-Çanakkale-Savaştepe Motorway (between Çanakkale-Savaştepe),
- (Ankara - İzmir Junction) - Bursa Highway,
- (Ankara - İzmir Junction) - Afyon - Antalya - Alanya Motorway (between Afyon - Antalya),
- (Ankara - İzmir Junction) - Afyon - Antalya - Alanya Motorway (between Antalya - Alanya),
- Şanlıurfa - Habur Motorway,
- Gerede - Merzifon Motorway,
- Delice - Samsun Motorway and
- Feasibility, corridor studies and preliminary project works of Aydın - Denizli-Burdur Motorway (Denizli - Burdur Section),
- Feasibility, corridor survey, EIA and preliminary project studies of Merzifon - Gürbulak Highway will be continued.
Highway Construction and Bridge Works:
Studies in 2013: In the 2013 Investment Program, there were 21 projects of the Directorate of Construction and Bridges. The total project cost in the Investment Program is 20,6 billion lira with the revisions made during the year. 2013 million TL has been provided, including additional allowances given in 656,8. All of this appropriation was spent during the year, and the total expenditure made as of the end of 2013 was 19.2 billion liras and 93,2% physical realization on projects basis and 100% monetary realization on the basis of appropriations.
With these allowances provided in 2013; 8 km of highway and 2 km of highway, 10 km of connection road, and 1,5 km of junction arm construction has been completed. Along with these highways, the construction was carried out on a total of 2013 km of motorways and connection roads, including 30,7 km of motorways, 20,8 km of connection roads, and 51,5 km of crossroads.
Gebze - Orhangazi - İzmir (including İzmit Gulf Crossing and connection roads) Highway was tendered on 09.04.2009 with the build - operate - transfer model. As a result of the tender, the Nurol - Özaltın - Makyol - Astaldi - Yüksel - Gökçay joint venture has been determined as the most suitable proposal and the joint venture Otoyol Yatırım ve İşlet A.Ş. The company named on duty was established. The contract for the implementation of the work was signed on 27.09.2010, the contract entered into force on 15.03.2013 and construction works are ongoing. The construction period included in the contract of the project is 7 years + 15 months, 4 years of operation is 22 years + 4 months. Also; The Construction Period Consultancy Services tender for the Gebze - Orhangazi - İzmir (including connection roads at the Izmit Gulf crossing) highway contract was held on 25.02.2013. As a result of the tender, Yüksel Proje - Emay - Chodail has made the most suitable bid. The consulting firm started its business on 17.05.2013. The Project; Studies continue in Gebze - Bursa and Manisa - İzmir sections in large and small art structures and earthworks.
The design works of the Suspension Bridge, various fabrication works and the production of caissons in the wet pool continue. Tunnel excavations are still being carried out in the 4 mirror in the Samanlı Tunnel within the scope of the project. The works of entrance and exit portal structures are continuing in Selcukgazi Tunnel and Tunnel excavation works are still going on in Belkahve Tunnel.
ICA IC İçtaş-Astaldi 3rd Bosphorus Bridge and North Marmara Highway, which will be tendered, Project Construction and loan procurement processes are being carried out in the Northern Marmara (including the 3rd Bosphorus Bridge) Highway Project Odayeri - Paşaköy (including the 3rd Bosphorus Bridge) section, and the loan will be provided in the near future in terms of financing. Following the completion of the loan agreement, construction works will be accelerated. The Consultancy Services Tender for the Construction Period of the Odayeri-Paşaköy (including the 3rd Bosphorus Bridge) Highway Project for the Northern Marmara (including the 3rd Bosphorus Bridge) was signed on 31.05.2013 and a contract was signed with the consultancy firm Yüksel Proje Chodai on 05.08.2013.
Izmir - Manisa State Highway Sabuncubeli Tunnel Project was tendered on 01.06.2011 according to the build - operate - transfer model. As a result of the tender held, Koçoğlu İnşaat A.Ş. - Makimsan Asfalt Taahhüt İnş.San.Tic.A.Ş. The assignment decision regarding the assignment to the Joint Venture was approved on 15 July 2011. As a result of the assignment decision, Sabuncubeli Tunnel investment and management A.Ş. The contract of the project was signed between this company and the General Directorate of Highways on August 19, 2011. The Consultancy Tender for the construction period of the project was made on 11.12.2012 and Temelsu Uluslararası Mühendislik Hizmetleri A.Ş. A contract was signed with the company on 11.03.2013. As of March, 45-m long cut-and-cover structure in the Soltüp Tunnel was completed as of March. In the basic upper half, 718 m in total and 763 m in total have been achieved. Tunnel excavation preparations are continuing in the Manisa portal. In addition, superstructure improvement and repair works were continued in various highway sections that were opened to traffic before, and the superstructure improvement of 150 km of highway sections in various sections was completed.
2014 Targets: In the 2014 Investment Program, there are 16 projects of the Directorate of Construction and Bridges, the total project cost in the Investment Program is 16,3 billion liras, the end of 2013 expenditure is 15 billion liras and the remaining project load is 1.3 billion liras. In 2014, the investment allowance per year is 487.657.000 lira.
In addition to these payments made in 2014, an additional investment of 450 million TL is needed. With these additional funds to be provided in 2014; It is aimed to complete the 44,9 km highway and connecting road, as well as the 18,4 km junction arm this year. Until the end of March 2014, a total of 2.609 km (excluding build - operate - transfer projects tenders) highway and connection roads were tendered and 2.575 km were opened to traffic.
A part of the 2.575 km road, which has been completed, has been transferred to the municipalities and part of it is in the State Roads network, and a total of 1.829 km, including 298 km of highway and 2.127 km of connection roads, is under the responsibility of Highway Maintenance Operation. In 2014, a total of 26,0 km of motorways and connection roads, including 18,9 km of motorways and 44,9 km of connection roads, and construction works will continue at the junction arm of 18,4 km. In addition, superstructure improvement and major repairs will be continued in various highway sections that were previously opened to traffic. In case of additional appropriation, it is aimed to complete the superstructure improvement of a total of 150 km of highway.
From Build - Operate - Transfer Highway Projects;
- Accelerating the construction works on the Gebze - Orhangazi - İzmir (including İzmir Gulf crossing and connection roads) Highway, which is assigned,
- Accelerating the construction works in the İzmir - Manisa State Highway Sabuncubeli Tunnel Project, which is assigned,
- Acceleration of the construction works for the North Marmara Motorway (including the 3rd Bosphorus Bridge) Project Odayeri - Paşaköy (including the 3rd Bosphorus Bridge) project,
- Northern Marmara (including the 3rd Bosphorus Bridge) Highway Project Kurtköy - Akyazı (including connection roads) and Kınalı - Odayeri (including connection roads) sections are planned to be tendered within the scope of the build - operate - transfer model.
- The Ankara - Niğde Motorway Project has been applied to the High Planning Council (YPK) and an announcement will be made after the YPK decisions are issued.
- Ankara - Samsun Motorway (Ankara - Delice Section) - Kınalı - Tekirdağ - Çanakkale - Balıkesir Motorway
- Aydın - Denizli - Burdur Motorway
projects were applied to the High Planning Council. Regarding these projects, revision studies are carried out in feasibility reports in line with the opinions conveyed to our General Directorate by the Ministry of Development.
- Ankara - İzmir Motorway, - Afyon - Antalya - Alanya Motorway,
- Sivrihisar - Bursa Motorway, - Şanlıurfa - Habur Motorway and Diyarbakır Connection,
- Gerede - Gerede - Merzifon Section of the Gürbulak Highway, - Delice-Samsun Section of the Ankara-Samsun Highway,
- Denizli - Burdur Section of Aydın - Denizli - Antalya Highway
The feasibility studies, corridor studies, EIA and preliminary project works have been tendered and the project works are continued.
The construction tenders of these projects will also be carried out with the build - operate - transfer model in 2014 and later years. The tender was completed in 2010 with the reinforcement works of 01,02 large art structures (03 bridges, 84 viaducts) on the 10 and 94 Motorways (between Kınalı and Anadolu Intersection), which were tendered in 2010 to be made with the National Budget. Earthquake reinforcement works for 04 large art structures (68 bridges, 49 viaducts and 15 tunnels) on the motorway (between Çamlıca and Gümüşova Junction) have been started. In total, 4 bridges and viaducts have been completed in 2011-2013. The tender for the reinforcement works against earthquake in 108 bridges and viaducts that have not been reinforced yet is planned to be carried out in 60.
In addition, maintenance, repair and structural reinforcement of the Bogaziçi and Fatih Sultan Mehmet Bridges, and the need for structural improvement studies in order to be able to provide services at the original design standards within the scope of the Engineering and Consultancy Services work have been realized. and repair and structural reinforcement works, and engineering and consultancy services work was taken into the investment program with 2010 E O40 300 DPT no.
In order to make improvement projects for improvement projects, the Engineering Consultancy Services on 18.07.2011, in order to carry out improvement design projects, have made Parsons Transportation Group INC., Which specializes in maintenance, repair and strengthening of suspended bridges. Construction and construction control tenders have been made according to the needs of the company.
Bosphorus and Fatih Sultan Mehmet Bridges Major Repair and Structural Reinforcement Project Construction work was signed on 25 November 2013 and started to work. 25 02 2014 contract work and contract work was signed on the contract signed by signing the contract.
Within the scope of the business in question:
Bosphorus Bridge;
- 236 hanger ropes (Diagonal hanger ropes will be made vertical)
- Strengthening the towers (to be reinforced with steel plates for the towers)
- Repair and strengthening of some parts of the deck
- Superstructure renewal (asphalt works)
- Establishing a moisture-proof system against corrosion for main cable and anchorage rooms
- Electromechanical works (elevator, wiring etc.)
At the FSM Bridge:
-Boya works (complete painting of the bridge)
- Main works such as the establishment of a dehumidifier system against corrosion for the main cable and anchorage rooms will be carried out.
Motorway Maintenance and Operation Studies:
03 As of the date of 2014 2.127 km is open to the operation of the motorway maintenance and operation of the highway. 2013-2014 winter snow and ice-fighting services were carried out by 764 machine-equipment and 179 art class personnel.
2013 OGS input as of the end of 156, 176 OGS output; 166 HGS entrance, 199 HGS check-in desk serves.
80 of the 48 Motorway Service Facilities on the Motorways were tendered by the Build-Operate-Transfer model in accordance with the Law No. 3465, and 20 of them were put into service according to the Law No. 2886.
23 service areas on the highways and 45 parking lots are available at 68.
2013 Year Studies:
Motorway maintenance and operation activities; and appropriations allocated from current and investment programs.
2013 103,8 million pounds in the current program has been allocated in accordance with the purpose of the whole and has been used and 100% realization has been achieved.
There are 3 main projects in the Investment Program and the total project cost is 525,624 million liras. In 2013, 17,6 million TL appropriation was spent for the investment program.
100 cash realization has been realized in the investment program. During 2013, maintenance and repair works were carried out from the current program. Within the scope of the projects included in the investment program, automatic and rapid transition systems were continued to be expanded on highways.
In addition, within the scope of the traffic safety project, guardrails, wires, horizontal and vertical traffic signs and maintenance operation plant repairs were made.
Automatic Transition System (OGS), Card Access System (KGS) and Fast Pass System (HGS):
Any vehicle class permitted to enter the highway can subscribe to OGS and HGS.
The distribution of HGS cards and OGS labels is done by bank branches according to vehicle classes. HGS System 17 was launched on 2012, 11 2013 on January XNUMX. Balances in the TCK KGS cards are transferred to the OGS accounts of the motorway users or to the HGS accounts in the PTT.
2014 Year Targets:
In 2014, 90,7 million TL was allocated from the current program. The total cost of the 3 main projects in the Investment Program is 557,1 million liras and the 2014 allowance is 11.5 million liras. Normal maintenance, repair and service works of the current enterprise with current appropriation will be carried out. Within the scope of the projects included in the investment program, wire fence, guardrail, horizontal and vertical marking works will be carried out.
Wage Collection Systems:
Within the scope of fee collection systems, the automatic pass system has been offered to the users since 1999 and the card pass system has been offered to the users since 2005, and KGS was abolished on 31 January 2013. HGS was put into operation on September 17, 2012. On 05 February 2014, Free Pass System has been established in Fatih Sultan Mehmet Bridge and testing works are continuing. As of February 2014, 2,1 million TL OGS and 5,1 million HGS subscribers have been reached, and a 20% discount in the Automatic and Rapid Transition System continues.
Highway Traffic Safety:
In 2013, 677.266 m² horizontal marking, 10.000 m² vertical marking, 500 Km guardrail and 500.000 m² wire repair and replacement is aimed.
Tunnel Operation:
The operation of the tunnels, which realize the productions with high construction technology, is another subject of expertise. From our tunnels with electrical, electronic and electromechanical systems; 2th year Selatin Tunnel under the responsibility of the 75nd Regional Directorate of Highways and Bayraklı The Tunnel is Bolu Tunnel, which is under the responsibility of the 4th Regional Directorate of Highways, TAG Tunnels, which are the responsibility of the 5th Regional Directorate of Highways, and Kırkgeçit Tunnels, which are the responsibility of the 6th Regional Directorate of Highways.
Highway Service Facilities:
In 2014; It is aimed to complete the build-operate-transfer tender of the 8 freeway service facility on the highways, and to tender the 5 motorway service facility by leasing method according to the 2886 Act. It is aimed to increase the service quality and revenue of the motorway service facilities, which are open to the operation, by increasing the type of service offered at the motorway service facilities, instead of only passing by the passerby.