Kayaş - Irmak - Kırıkkale - Çetinkaya Electrification Project 6. and 7. section evaluation work has been completed

TCDD Kayaş - Irmak - Kırıkkale - Çetinkaya Electrification Project 6. and 7. section evaluation work has been completed
The. Kayaş - Irmak - Kırıkkale - Çetinkaya Electrification Plant Construction D tender to be carried out by the General Directorate of Turkish State Railways (TCDD) will be carried out by 6. and 7. and the evaluation studies have been completed.
According to the information received by the Investments Magazine; 6. 42.069.600 lira, 7. The company won the joint venture of Ultra Technology - Nuhoglu Construction with the offer of 40.288.200 liras.
As it is known, the tender 1. 30.368.067 pounds quoted with Şahin Yılmaz - Emre Ray joint venture, 2. The company won the joint venture of Ultra Technology - Nuhoglu Construction with the offer of 27.730.000 liras. The officials we met at this stage were 1., 2., 6. and 7. they will be notified to the companies after the approval of the management for the results of the sections.
It will be remembered that the tender 3.4.5. Yapı Merkezi company and 8. Ultra Technology company, which is a part of the contract signed. Contract winners and contract prices were as follows:
1. Building Center
3. 24.728.350 Offer
4. 24.606.694 Offer
5. 17.353.953 Offer
2. Ultra Technology - Nuhoğlu Construction
8. 53.450.000 Offer
The approximate cost is 1. 44.063.670 for section, 2. 43.007.527 for section, 3. Section 36.122.297 lira, 4. part 36.194.475,50 lira, 5. 25.328.908 for section, 6. for 57.998.073, 7. 55.524.483 for section, 8. The companies that participated in the tender which was determined as 82.315.810 lira for the part were as follows:
1. E + M - Aykon Electric
2. Semi (Spanish)
3. Siemens A.Ş.
4. View Şahin's Full Profile
5. Ultra - Nuhoğlu İnş.
6. Building Center
Ref .: Yachts Magazine 1173 / I 17 March 2014 (AP)


Source : I www.yatirimlar.co



Be the first to comment