To apply for approval of Ministry of Development for the investment of Kırıkkale - Samsun Railway Project in 2014 year

AYGM Kırıkkale - Samsun Railway Project. Approval of the Ministry of Development will be applied for the project to be included in the 2014 investment program.


Work on the X Approximately 450 km-long Kırıkkale-Samsun Railway Line Project tarafından to be realized by the General Directorate of Infrastructure Investments (AYGM) is in progress.

According to the information received from Investments Magazine; EIA Report prepared by MGS Proje Mühendislik company was approved by the Ministry of Environment and Urbanization.

Approval of the Ministry of Development will be applied for the project to be included in the 2014 investment program. Experts will start work on expropriation plans, explorations and quantities, and the tender announcement can be made in the second half of 2014.

Survey project and engineering services The project, carried out by Yüksel Proje, consists of KırıkkaleSamsun main line and two connection lines (Yerköy Connection Line and Amasya - Turhal Line).

54 bridges-viaducts, 21 tunnels and 5 stations will be included in the scope of the project. The railway will be constructed of electric and double track. The trains will be able to travel at 250 km per hour in passenger transport and at 80 km in freight transport. The project is planned to be put into service in 2018.

Reference: Investments Magazine 1001 / 25 October 2010 (SB)

Source : I www.yatirimlar.co