It turned out that the Ministry of Internal Affairs had kept the additional appropriation request for the Izmir Metro for 7 months. Despite the Izmir Metropolitan Municipality's request for an increase in allowance dated 31 August 2012, the Governorship of Izmir sent the Ministry of Interior in September; The Ministry notified this request to the Council of Ministers exactly 7 months later. Upon this letter dated March 1, 2013, the Council of Ministers approved the additional appropriation request for the Izmir Metro with its decision on March 11.

The government finally approved the expected increase in exploration for the Izmir Metro. Izmir Metropolitan Municipality's demand for increase in discovery entered into force after being published in today's Official Gazette.

In the decision, “the annexed Decision regarding the permission to increase the work up to 2% of the contract price in İzmir Light Rail System 39,26nd Stage Project Tunnel Works and İzmir Spor and Hatay Stations Supply Construction Work; According to the article of the Ministry of Internal Affairs dated 1/3/2013 and numbered 6569, according to Article 4735 of the Public Procurement Contracts Law numbered 24, it was decided by the Council of Ministers on 11/3/2013. It was said.

After the approval of the Council of Ministers to the discovery increase demand that İzmir Metropolitan Municipality has been waiting for about 8 months, the contractor company stopped the construction of the 1st phase metro line of the Üçyol-Üçkuyular line due to financial difficulties.

In the scope of the 1 tender of the Üçyol-Üçkuyular line in İzmir, the two stations, tunnel construction, the Metropolitan Municipality, which previously approved the increase in the exploration rate of 20 on the basis of the 19.35 in relation to the laying of the rails, In August, 31 applied to Izmir Governor's Office with a letter. The governor's office sent the letter to the Ministry of the Interior to be presented to the Council of Ministers, which was approved by 4 in September for the recognition of up to 40.

APPROVAL ON 3 DAY IN ISTANBUL

While the approval of Izmir was approved in 7 months, the Council of Ministers in Istanbul under the 4th Levent- Darrüşşafaka Metro Project, Istanbul Metro III. Stage 4. Levent- Ayazağa Section, Seyrantepe Storage Area and Warehouse Connection Lines Supply construction and Electromechanical Systems Procurement, Installation and Commissioning works project permitted the increase in the work up to 31.30 percent of the contract value within 3 days in August.