TCDD Kayseri Boğazköprü Ulukışla Yenice Mersin Yenice Adana Toprakkale Line Electrification Project 2. 3 and 5. Evaluation of the section has been completed

TCDD Kayseri Boğazköprü Ulukışla Yenice Mersin Yenice Adana Toprakkale Line Electrification Project 2. 3 and 5. Evaluation of the section has been completed
Turkish State Railways (TCDD)
01 on February 2012 Day offers
“Kayseri - Bogazkopru - Ulukisla - Yenice, Mersin -
Yenice - Adana - Toprakkale
Construction of Electrification Plants
related new developments recorded.
According to the information received by the Investments Magazine; The tender 2.,
3, and 5. evaluation studies
was submitted to the Board of Directors for approval. Necessary
after the approval of the tender results
to be notified to the companies. As it is known,
09 October 2012 with technology company 1. for part
24.731.000 lira, 4. for part 32.432.000 lira
contract signed. 6 of the tender. winning part E + M
Electricity - Aykon Elektrik joint venture with 15 August
Contract on 2012 pounds on 52.278.954
He was signed. Şahin Yılmaz - Emre Ray
initiative appealed to the JCC for the result of the tender,
The JCC also filed an appeal for the outcome of the tender 1. section
rejection of the appeal complaint;
corrective for the 2, 3 and 5 parts of the tender
regarding the determination of the transaction and the 4 part of the tender
had decided to refuse the application.
As can be remembered, the approximate costs 1. for part
33.752.709 lira, 2. 24.203.377 lira for part, 3. portion
32.449.409 lira, 4. 46.361.740 lira for part, 5. portion
for 37.273.812 lira, 6. 60.436.750 for pounds
other companies participating in the tender were as follows:
1. Dalkıranlar Construction
2. Semi (Spanish)
3. Siemens A.Ş.
4. View Şahin's Full Profile
Ref .: Investments Magazine 103 / 15 October 2012 (APE)


Source : I www.yatirimlar.co


Railway News Search

Be the first to comment

Comments