In the Balçova Cable Car Facilities, which was closed in 2007 on the grounds of lack of life safety, not even a nail has been hammered for 5 years due to objections and tender cancellations. While the last tender for the facilities has been cancelled, the Metropolitan Municipality will go to the 4th tender in the coming months. The construction of the Balçova Cable Car Facilities on Dede Mountain, which was closed in 2007 upon the report of “No life safety” prepared by the İzmir Branch of the Chamber of Mechanical Engineers of İzmir Metropolitan Municipality, was again left for another spring.

Due to the objections experienced and consecutive cancellations in the specification of the construction period determined as 1 years, 5 5 times in the service could be opened once the last tender for the facility was canceled.

The court found the JCC right

The Public Procurement Authority (JCC) received the previous tender from STM, Ankara 14. In the lawsuit he filed with the Administrative Court, he had appealed before the Ankara Regional Administrative Court. Subsequently, he sent a letter to the Metropolitan Municipality, saying, ediy Apply the judgment. Sign contract with STM. ST The full 5 year-end of the difficult auction process was over, the decision of the Regional Administrative Court turned everything upside down. The court justified the JCC and abolished the STM's decision to stop the execution.
A nail didn't even crash

That being the case, it literally turned into arabic hair. Previously, “Apply the court order. "Give the tender to STM" and sent a second letter this time and said, "Cancel the tender that STM has won". The cable car tender, which has been the subject of objections many times until today, was left to another spring with the last letter sent by the KİK. Thus, even a nail could not be hammered into Balçova Ropeway Facilities, although more than 2010 years and 2 tenders have passed since the first tender process that started in February 3. While Büyükşehir started a transaction in line with the letter sent by the KİK, it decided to hold the 4th tender in the coming months.

Here is the step-by-step 5 years

  • The last tender process that will ensure the rebuilding of the Teleferik, which has been closed for 5 years and has been closed for 2010 years, at the summit of the Dede Mountain, where the most beautiful view of Izmir is seen, began in XNUMX.
  • STM won the first tender held by the Metropolitan Municipality in 2010. When it came to the contract phase with the company, the Metropolitan Municipality canceled the tender because the company could not deliver the required documents and documents.

2nd tender was held in February

The municipality held its second tender in February 2012. STM Sistem Teleferik Montage ve Turizm A.Ş., which made the lowest bid of 10 million 225 thousand TL. won. Doppelmayr Seilbahnen Gmbh, which made the highest bid in the tender with 14 million 400 thousand TL, objected to the GCC. The JCC canceled the tender on April 9, 2012 on the grounds that the municipality's approximate cost calculation was erroneous and it had to be calculated one by one over unit prices.
Upon the cancellation of the tender, Izmir Metropolitan Municipality made a new tender on 7 June 2012. Three companies, STM Teleferik, Doppelmayr, Leitner, as well as Batholet, participated in the tender. Meanwhile, STM took the decision of the PPL regarding the cancellation of the tender to the court.

The result of the appeal was expected

Ankara 14. The Administrative Court dismissed the firm's objection and stopped the execution of the decision of the JCC which canceled the tender. Then the Metropolitan Municipality, 7 3 in April. did not receive financial proposals in the tender. The question of how the Metropolitan Municipality will follow in the next period was the subject of the decision of the municipality. KIK sent a letter to the Metropolitan Municipality of Ankara 14. He asked the Administrative Court to implement the decision to 'stop the execution'. Then the Metropolitan Municipality received the offers 4. canceled the tender. Then the cancellation decision was communicated to the participating firms.

Meanwhile, the JCC, Ankara 14. The Administrative Court objected to the decision of the Administrative Court to stop the execution. The municipality decided to wait for the result of the appeal to the Regional Administrative Court, despite the fact that the JCC had applied to the court in order not to experience any problems in the future.

2 years may be shifted

All of this happened right after it is happened. The Regional Administrative Court abolished the decision of the GCC to suspend the execution of the decision. Then the Metropolitan Municipality Ankara 14. Implement the decision of the Administrative Court to stop the execution. STM signed a contract with the letter, '' he said this time 'cancel the tender' he said. The Metropolitan Municipality decided to cancel the tender. Then he started the new tender preparations.
Although 2010 months have passed since the first tender process, which started in February 34, with the latest incident, even a barley-length road could not be achieved regarding the renovation of the facilities. The facilities, whose construction period was 1 year, caused the cable car pleasure of İzmir residents to be postponed for 2014 more years, with the most optimistic estimation, with the consecutive objections and tender cancellations.

How will the facility be renewed?

With the new system to be installed in Balçova Teleferik Facilities, the landing capacity will be increased to 400 thousand 2 per hour. Thus the total annual capacity 400-300 will increase to a thousand persons. The old 500 passenger cabinets will be replaced by 600 cabinets. In the new ropeway line, the automation system stops the cabs automatically and immediately interferes. The ticket halls at the entrance of the facility will be renewed within the scope of the tender. Studies will be completed in a year.