Estram Project and Technology

The ESTRAM Project was completed on 20 month. [2]

History of Estram Project

Contract start date (NTP) → 11 July, 2002
Start of excavation (Bazaar area) → 15 August, 2002
Addition of the Opera lever → 15 August, 2003
First vehicle coming to Eskişehir → December 10, 2003
Completion of the project → 27 June, 2004
Start of flights → 24 Range, 2004
Estram Technology

The tram has four times longer braking distances than rubber-wheeled vehicles.

Vehicle Energy Supply: Overhead Line DC 750 V
Overhead line height: 5,90 m
Overhead line security height: 4,40 m

Tool name: Flexity Outlook
Length: 29,5 m
Weight (empty): 35.800 kg
Width: 2,3 m

Vehicle height: 3,5 m
Engine power: 105 kw four engine
Maximum speed of the vehicle: 70 km
Tram-to-tramway point: Çarşı Durağı

Line Length: 15.727 m
Passengers carried per day: 110.000 - 120.000 people… Pass (2004)
251.000 people… Pass (2020)
2.3 km / person… km / pass