Bandırma-Bursa-Ayazma-Osmaneli High Speed ​​Train Project

Bandırma-Bursa-Ayazma-Osmaneli High Speed ​​Train Project

Bandırma-Bursa-Ayazma-Osmaneli High-Speed ​​Line It is aimed to facilitate transportation between metropolitan cities such as Ankara, Izmir, Istanbul and Bursa and to reduce travel time. With the completion of the project, the existing operating problems on the outline will be eliminated and the direct link between Asia and Europe will be provided at the same standards. Another aim is to ensure that the high-speed train line provides a safer and more comfortable transportation by reducing problems such as traffic accidents and air pollution caused by the intensity of road transport in the region.

THE TENDER PROCESS

In order to connect Bursa Province and Bandırma Port to our country's railway network, as the first step of the Bandırma-Bursa-Ayazma-Osmaneli High Speed ​​Train Project, the infrastructure construction tender of the Bursa-Yenişehir High Speed ​​Train Project has been completed and construction works have started.

As a first step of the project, the construction tender for Yenişehir Osmaneli / Bilecik section is planned to be continued, which will be the continuation of Bursa-Yenişehir Line and which will connect Yenişehir to Ankara Istanbul High Speed ​​Line.

Source: hizlitren.tcdd.gov.tr

LAST STATUS

Yenişehir- Bursa: Location was delivered on 13.01.2012. Route application studies are in progress.

Yenişehir- Osmaneli: Location was delivered on 29.12.2011. 10.05.2012 3 corridor has been approved and the route studies have been started.

Bandırma- Bursa: Project works are carried out by the General Directorate of Infrastructure Investments.