Izmir's ropeway tender turns to tangle

Ankara 14. The Administrative Court stopped the decision of the GCC to cancel the tender in February 2012. İzmir Metropolitan Municipality in the preparation of the tender did not receive the financial offers of the participants İdare
The tenders to rebuild the ropeway facilities with modern technology were confused. Until today, the renovation of the cable car plant has been postponed twice.
The tender held in February 2012 was awarded to STM Sistem Teleferik Montage and Turizm A.Ş., which gave the lowest bid of 10 million 225 thousand TL. kazanwas. Doppelmayr, who made the highest bid in the tender, objected to the GCC. On 9 April, the KİK canceled the tender on the grounds that the municipality's approximate cost calculation was incorrect and that it had to be calculated individually over unit prices.

He sued, joined

Upon the cancellation of the tender, the Metropolitan made a new tender in June 2012. Three companies that took part in the first tenders, STM Teleferik, Doppelmayr, Leitner, as well as a Batholet company participated in the tender. The tender canceled by the KİK kazanWhile STM Sistem participated in the new tender, on the other hand, it filed a lawsuit against the KİK for the stay of execution and annulment of the decision. The 14th Administrative Court of Ankara, by majority, stopped the execution of the KİK's annulment decision. The court decided that the renovation of the cable car is a special job and that the method used by the municipality in calculating the approximate cost is correct. While the cancellation decision of the KİK stopped the execution, the Metropolitan Municipality did not receive a financial offer in the new tender.

The JCC will also appeal

JCC, Ankara 14. The Administrative Court of Ankara will appeal against the decision of the Administrative Court. The final decision will be given by the State Council. Izmir Metropolitan Municipality will continue the new tender in this process. Ankara Regional Administration and the Council of State will wait for the final decision. If the JCC decision is canceled, the result of the first tender will be valid.

Capacity to fold

With the renewal of the cableway facility, the 400 2 will be upgraded to 400 per hour, and the 300 bin 500-600 will increase to 4-8. 12 or XNUMX cabinets will be used instead of XNUMX passenger cabinets. In the new ropeway line, the ropes will automatically stop and there will be immediate intervention.

Source : I www.gazetemizmir.co