İzmir Light Rail System Signalization Projects: İZMİR HRS.II STAGE TUNNEL WORKS AND İZMİR SPOR HATAY STATIONS SUPPLY CONSTRUCTION WORK and İZMİR HRS. 3. STAGE 1. SECTION BORNOVA HOSPITAL - SUPPLEMENTARY CONSTRUCTION BETWEEN EVKA 3 STATIONS (SIGNALIZATION WORKS)

Izmir LRTS, 2000 units and warehouses in service since 10, 11 km. long line.

In addition to the existing system, a total of 3 km in 7,4 separate stages. line will be added. Signalization System Assembly and Test & Commissioning works of the additional lines are carried out within the scope of our company.

Within the scope of signaling systems to be established:

  • 85 km. Cable,
  • 52 pieces Signal,
  • 12 Scissor Motors & Local Control Panels,
  • 190 pieces Balis,
  • 46 pcs Impedance Bond,
  • 116 pcs Isolated Alloy,
  • 232 line line circuit,
  • Signalization Panels, Rail Circuits, UPS Systems, System Installations, System Integrations,
  • Testing and Commissioning

Etc., as are studies.

In our work, work quality and safety is an important issue for us and our aim is to complete our projects ler 0 ler work accident and successfully on time.

BORNOVA - EVKA3 LRTS PROJECT

Bornova - Evka3 extension, about 2,2 km. is a line with an 2 station (University - Evka3).

ÜÇYOL - HATAY LRTS PROJECT

Üçyol - Hatay extension, about 1,7 km. length of 2 station (Izmirspor - Hatay) is a line.

GÖZTEPE - FAHRETTİN ALTAY LRTS PROJECT

Göztepe - Fahrettin Altay extension, about 3,5 km. is a line with 3 station (Göztepe - Polygon - F.Altay).