Avcılar-Beylikdüzü Metrobüs 3 month will be delayed!

At the groundbreaking ceremony, the 29 is said to be taking place in October, and the completion date in October is postponed to December.

Although the concrete and asphalt process was finished in most of the line, concrete and asphalt were broken and new sewer pipes were laid because the sewer pipes under the line were damaged.

PIPES CHANGED AGAIN

According to the information received from the authorities, even the most of the sewer pipes were damaged and rebuilt. The change of sewer pipes starting at the beginning of February continues at full speed. During the works, broken pipes and excavation were discharged from Saadetdere junction.

UPPER PASSES CANNOT BE OPENED

On Monday, the Istanbul Metropolitan Municipality said in an official statement, kullanım Authorities have stated that they are aiming to open all the construction vehicles in the region to the citizens of 24 February 2012 Friday. Pazartesi

The works on the parcel in the parcels 25 continued on Saturday February. In fact, the opening of the new overpasses in a short time seems to be impossible for now. In the photo gallery you can see the latest status of the overpasses in the line.

THREE MONTHS MORE

Avcılar-Beylikdüzü Metrobus line when the official information about the opening of the work, while the ongoing team has a work plan of three months passed. Before the Mayor of Beylikdüzü Yusuf Uzun, according to the contract, the official delivery date of March was reported.

Apologized for shaking in February

Istanbul Metropolitan Mayor Kadir Topbaş said that the line will open in February in January and apologized for the delay.

Source: News 7